An ACEC Partnering Committee meeting was held on October 17, 2007 with Hal Godwin, Assistant to the Administrator of Sussex County, regarding the revisions to the Sussex County Comprehensive Plan.  Meeting attendees included:

 

Hal Godwin                             Sussex County

Doug Warner                          Duffield & Associates

Stephen Lee                            Century Engineering

Bruce Horne                           ECI

Christopher Weeks                 Becker Morgan

Jessica Nichols                      Karins and Associates

 

The following items were discussed:

 

Status of Comprehensive Plan Approval

 

Currently Sussex County is in the process of conducting meetings with all of the municipalities to insure that the growth areas represented in the Draft Comp plan will coordinate with the future annexation area of the municipalities.  There will be a DelDOT presentation Tuesday October 23rd at Sussex County Planning and Zoning regarding the mobility element of the plan. Once the meetings are complete and the Draft will be revised and submitted to PLUS for review and comment from the State.  After PLUS the revised (if necessary) Draft will be submitted to Sussex County Planning & Zoning and there will be a hearing held for public comment and for Planning & Zoning to make a recommendation to Sussex County Council.  Another hearing will be held with Council once Planning & Zoning has made a recommendation.  The goal is to have the Comp plan approved by Council by January of 2008; however, Mr. Godwin stated that they had an extension to April 2008 and that that is probably a more realistic timeframe. 

 

The codifying of the guidelines in the Comprehensive Plan into Ordinances by Sussex County Planning & Zoning

 

Questions were raised regarding the timeline for Planning and Zoning to create/approve the ordinances which will be suggested in Comprehensive Plan once it is approved.  It was stated that many of the ordinances that were suggested in the 2002 Comprehensive Plan were never approved as ordinances by Planning & Zoning.  Mr. Godwin mentioned that he believes there is an 18 month period in which P&Z has to codify the ordinances suggested in the Comp Plan; however, he is unsure of when that 18 month period begins.

 

Regional Planning

 

Regional Planning was discussed with regards to transportation, water and sewer infrastructure as well as regional stormwater facilities.  Impact fees and developer contribution for improvements both on and off-site improvements was talked about.  Lengthy discussion regarding the coordination between the Sussex County Engineering Department and Artesian and Tidewater for sewer infrastructure was had.  Most attendees agreed that it is more desirable to have a large regional system with adequate conveyance systems than many private systems and pump stations scattered around the County, which is currently the trend.  Mr. Godwin suggested that Sussex County Engineering Department should have more control over the sewer system design/construction even if it is to be an Artesian or Tidewater system.  Concerns from the engineers were that this would require another review from the Engineering Department and also that there is a lack of confidence in the Engineering Departments ability to review and handle this responsibility.

 

Source Water Protection Ordinance

 

Sussex County is currently working on a Source Water Protection Ordinance.  A committee has been formed to work on the ordinance.  The diversity of the members of the committee was questioned as the vast majority of committee members own a huge amount of land in Sussex County and would be adversely affected by an ordinance which limits what they can do on their land.  Mr. Godwin seemed fairly confident that the draft ordinance would be denied by DNREC.  The timeframe for approval of a Source Water Protection Ordinance is unknown.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 Website:  www.cecde.org

E-mail:     cecde@dea.net

 

 
 

 


 Website:  www.cecde.org                                 P. O. Box  1858                                  Phone:                  302-730-8384

 E-mail:    cecde@dea.net                            Dover, DE  19901-1858                            Toll Free:        302-442-3233

                                                                                                                         Fax:              302-734-0580

 Website:  www.cecde.org

E-mail:     cecde@dea.net