MEMORANDUM

 

To:                   CEC/DE Executive Committee

From:              Stephen L. Johns, P.E., P.L.S.

Date:                August 3, 2009

Re:                   NCC Special Services Partnering Meeting Minutes, July 27, 2009

 

 

 

At 2:00 PM, on Monday, July 27, 2009, the NCC Partnering Committee met with New Castle County’s Department of Special Services. The following topics were discussed:

 

1.         Sanitary Sewer Design Review Time Frames – Special Services is currently completing plan reviews in 4 to 5 weeks.

 

2.         Northern Sewer District – All project are moving along according to schedule. The Surrey Park Interceptor project is scheduled to be advertised in afew weeks. They are also starting a rehab program.

 

3.         Southern Sewer District – The County is currently not expecting any additional sewer work in Southern New Castle County in the foreseeable future.

 

4.         Checklists, Guidelines, and Design Policies – Jason is close to finalizing revisions to the checklist and guidelines, and additional details are being finalized. The contractual conditions in the standard specifications is being revised and is almost done. The County is also starting to work on revising and updating the technical specifications, adding new material references, etc.

 

5.         Next Meeting – Our next meeting is scheduled for October 26, 2009 at 2:00 PM.

 

 

W:\slj\CEC\NCC Partnering Committee\NCC Partnering Committee Minutes SS 09-07-27.doc